{"id":49088,"date":"2025-12-15T12:51:26","date_gmt":"2025-12-15T18:51:26","guid":{"rendered":"https:\/\/www.projectmanager.com\/?p=49088"},"modified":"2025-12-23T10:52:12","modified_gmt":"2025-12-23T16:52:12","slug":"risk-management-plan","status":"publish","type":"post","link":"https:\/\/www.projectmanager.com\/blog\/risk-management-plan","title":{"rendered":"How to Make a Risk Management Plan (Template Included)"},"content":{"rendered":"<p>You identify them, record them, monitor them and plan for them: risks are an inherent part of every project. Some project risks are bound to become problem areas\u2014like executing a project over the holidays and having to plan the project timeline around them. But there are many risks within any given project that, without risk assessment and risk mitigation strategies, can come as unwelcome surprises to you and your project management team.<\/p>\n<p>That\u2019s where a risk management plan comes in\u2014to help mitigate risks before they become problems. But first, what is <a href=\"\/blog\/risk-management-process-steps\">project risk management<\/a>?<\/p>\n<h2>What Is a Risk Management Plan?<\/h2>\n<p>A risk management plan defines how the project\u2019s risk management process will be executed. That includes the <a href=\"\/training\/create-and-manage-project-budget\">budget<\/a>, tools and approaches that will be used to perform risk identification, assessment, mitigation and monitoring activities.<\/p>\n<div class=\"template-download-holder\">\n\t<div class=\"template-download-image-holder\">\n\t\t<img loading=\"lazy\" decoding=\"async\" width=\"1600\" height=\"900\" src=\"\/wp-content\/uploads\/2023\/09\/Risk-management-plan-template-1.jpg\" class=\"attachment-large size-large\" alt=\"Risk Management Plan Template\" srcset=\"\/wp-content\/uploads\/2023\/09\/Risk-management-plan-template-1.jpg 1600w, \/wp-content\/uploads\/2023\/09\/Risk-management-plan-template-1-600x338.jpg 600w, \/wp-content\/uploads\/2023\/09\/Risk-management-plan-template-1-300x169.jpg 300w, \/wp-content\/uploads\/2023\/09\/Risk-management-plan-template-1-768x432.jpg 768w, \/wp-content\/uploads\/2023\/09\/Risk-management-plan-template-1-1536x864.jpg 1536w, \/wp-content\/uploads\/2023\/09\/Risk-management-plan-template-1-450x253.jpg 450w, \/wp-content\/uploads\/2023\/09\/Risk-management-plan-template-1-384x216.jpg 384w, \/wp-content\/uploads\/2023\/09\/Risk-management-plan-template-1-800x451.jpg 800w\" sizes=\"auto, (max-width: 1600px) 100vw, 1600px\" \/>\t<\/div><p class=\"intro\">Get your free<\/p>\n<h3>Risk Management Plan Template<\/h3>\n<p class=\"subtitle\">\n\tUse this free Risk Management Plan Template to manage your projects better.<\/p>\n\t<a class=\"button green\" href=\"https:\/\/www.projectmanager.com\/templates\/risk-management-plan-template\">Get the template<\/a>\n<\/div> \n\n<p>&nbsp;<\/p>\n<p>A risk management plan describes all the activities that will be taken throughout the process of managing project risks. Project risk management activities can be grouped into the following categories:<\/p>\n<ul>\n<li><strong>Risk Planning:<\/strong> Before risks can be managed, the overall approach must be defined. The risk management plan establishes the methodologies, roles, responsibilities, budget allocation and timing for all risk management activities throughout the project life cycle.<\/li>\n<li><strong>Risk Identification:<\/strong> The first step to managing project risks is to identify them. The risk management plan explains the tools and data sources, such as information from past projects or subject matter experts&#8217; opinions to estimate all the potential risks that can impact the project.<\/li>\n<li><strong>Risk Assessment:<\/strong> Once the project risks are identified, they need to be prioritized by looking at their likelihood and level of impact. In most cases, the risk management plan includes a risk assessment matrix to do so.<\/li>\n<li><strong>Risk Mitigation:<\/strong> Now it\u2019s time to create a contingency plan with <a href=\"\/blog\/mitigate-risk-project\">risk mitigation<\/a> actions to manage your project risks. You also need to define which team members will be risk owners, responsible for monitoring and controlling risks.<\/li>\n<li><strong>Risk Control:<\/strong> Once risk mitigation responses are in place, they must be actively controlled. The risk management plan describes how risk responses will be executed, evaluated for effectiveness and adjusted as project conditions or risk exposure change.<\/li>\n<li><strong>Risk Monitoring:<\/strong> Risks must be monitored throughout the project life cycle so that they can be controlled. The risk management plan describes the procedures, tools and techniques to monitor the occurrence and mitigation of project risks.<\/li>\n<li><strong>Risk Ownership:<\/strong> To ensure accountability, risks must be assigned to specific team members. The risk management plan defines risk owners and outlines their responsibilities for tracking, monitoring and implementing approved risk response actions.<\/li>\n<li><strong>Risk Reporting:<\/strong> Risk information must be shared clearly and consistently with stakeholders. The risk management plan describes how risks will be reported, escalated and communicated to support timely awareness and informed decision-making.<\/li>\n<\/ul>\n<p>Even one risk can jeopardize the entire <a href=\"\/guides\/project-planning\">project plan<\/a>. There isn\u2019t usually just one risk per project, either; there are many risk categories that require assessment and discussion with stakeholders. That\u2019s why risk management needs to be both a proactive and reactive process that is constant throughout the project life cycle.<\/p>\n<h3>Manage Risks and Projects Online with ProjectManager<\/h3>\n<p>For example, it&#8217;s easy to create a risk register using online project management software. Use the risk list view on <a href=\"\/\">ProjectManager<\/a> to capture all project risks, add their priority level and assign a team member to identify and resolve them. Then manage those risks alongside detailed project plans with in-depth data.<\/p>\n<ul>\n<li>Manage projects in five different views: Gantt, sheet, list, kanban and calendar<\/li>\n<li>Track and report on tasks and risks with dashboards<\/li>\n<li>Give stakeholders first-hand access to data and progress with free guest licenses. <a href=\"https:\/\/www.projectmanager.com\/freetrial?edition=d\">Try it free<\/a><\/li>\n<\/ul>\n<figure id=\"attachment_70161\" aria-describedby=\"caption-attachment-70161\" style=\"width: 2560px\" class=\"wp-caption aligncenter\"><a href=\"https:\/\/www.projectmanager.com\/freetrial?edition=d\"><img loading=\"lazy\" decoding=\"async\" class=\"wp-image-70161 size-full\" src=\"\/wp-content\/uploads\/2024\/03\/CTA-light-mode-risk-view.png\" alt=\"Risk management in ProjectManager\" width=\"2560\" height=\"1411\" srcset=\"\/wp-content\/uploads\/2024\/03\/CTA-light-mode-risk-view.png 2560w, \/wp-content\/uploads\/2024\/03\/CTA-light-mode-risk-view-600x331.png 600w, \/wp-content\/uploads\/2024\/03\/CTA-light-mode-risk-view-1600x882.png 1600w, \/wp-content\/uploads\/2024\/03\/CTA-light-mode-risk-view-300x165.png 300w, \/wp-content\/uploads\/2024\/03\/CTA-light-mode-risk-view-768x423.png 768w, \/wp-content\/uploads\/2024\/03\/CTA-light-mode-risk-view-1536x847.png 1536w, \/wp-content\/uploads\/2024\/03\/CTA-light-mode-risk-view-2048x1129.png 2048w, \/wp-content\/uploads\/2024\/03\/CTA-light-mode-risk-view-450x248.png 450w\" sizes=\"auto, (max-width: 2560px) 100vw, 2560px\" \/><\/a><figcaption id=\"caption-attachment-70161\" class=\"wp-caption-text\">Manage risks alongside your project with ProjectManager. <a href=\"\/\">Learn more<\/a><\/figcaption><\/figure>\n<h2>What Is the Purpose of a Risk Management Plan?<\/h2>\n<p>The purpose of a risk management plan in project management is to define how risks will be systematically identified, analyzed, prioritized, responded to and monitored throughout the project lifecycle.<\/p>\n<p>It establishes a consistent approach to managing uncertainty, protects project objectives related to scope, schedule, cost and quality, and supports informed decision-making by clarifying risk ownership, thresholds and response strategies. While its primary role is project-focused, it can also support broader organizational risk awareness when projects operate in complex or regulated environments.<\/p>\n<h2>When to Use a Risk Management Plan<\/h2>\n<p>A risk management plan originated in project management, where it formalizes how risks are identified, analyzed, prioritized and addressed to protect project objectives. Over time, its structured, repeatable approach proved valuable beyond projects.<\/p>\n<p>Today, organizations use risk management plans whenever uncertainty must be managed deliberately, including operations, construction, IT, finance and compliance.<\/p>\n<ul>\n<li><strong>Project risk management plan: <\/strong>Defines how project-specific risks are identified, assessed and managed to protect scope, schedule, cost and quality objectives throughout the project lifecycle.<\/li>\n<li><strong>Business risk management plan: <\/strong>Addresses operational and strategic risks affecting ongoing business activities, focusing on continuity, process stability, compliance and performance rather than time-bound deliverables.<\/li>\n<li><strong>Enterprise risk management plan: <\/strong>Provides an organization-wide framework to identify, assess and govern risks aligned with strategic objectives, risk appetite and executive-level decision-making.<\/li>\n<li><strong>Financial risk management plan: <\/strong>Focuses on identifying and mitigating risks related to budgets, cash flow, funding, pricing and financial exposure that could impact organizational or project viability.<\/li>\n<li><strong>IT risk management plan: <\/strong>Manages risks related to information systems, cybersecurity, data integrity and system availability, emphasizing controls, incident response and technology resilience.<\/li>\n<\/ul>\n<p>In these contexts, the plan provides a consistent framework for anticipating threats, evaluating exposure, defining response strategies and monitoring risk over time, even when no project timeline exists.<\/p>\n<h2>Free Risk Management Plan Template<\/h2>\n<p>This <a href=\"https:\/\/www.projectmanager.com\/templates\/risk-management-plan-template\">free risk management plan template<\/a> will help prepare your team for any risks inherent in the project. This Word document includes sections for your risk management methodology, risk register, risk breakdown structure and more. It&#8217;s so thorough, you&#8217;re sure to be ready for whatever comes your way. Download the template today.<\/p>\n<figure id=\"attachment_68083\" aria-describedby=\"caption-attachment-68083\" style=\"width: 600px\" class=\"wp-caption aligncenter\"><a href=\"https:\/\/www.projectmanager.com\/templates\/risk-management-plan-template\"><img loading=\"lazy\" decoding=\"async\" class=\"wp-image-68083 size-medium\" src=\"\/wp-content\/uploads\/2023\/09\/risk-management-plan-template-for-word-screenshot-600x564.jpg\" alt=\"Risk management plan template ProjectManager\" width=\"600\" height=\"564\" srcset=\"\/wp-content\/uploads\/2023\/09\/risk-management-plan-template-for-word-screenshot-600x564.jpg 600w, \/wp-content\/uploads\/2023\/09\/risk-management-plan-template-for-word-screenshot-300x282.jpg 300w, \/wp-content\/uploads\/2023\/09\/risk-management-plan-template-for-word-screenshot-768x722.jpg 768w, \/wp-content\/uploads\/2023\/09\/risk-management-plan-template-for-word-screenshot-450x423.jpg 450w, \/wp-content\/uploads\/2023\/09\/risk-management-plan-template-for-word-screenshot.jpg 1338w\" sizes=\"auto, (max-width: 600px) 100vw, 600px\" \/><\/a><figcaption id=\"caption-attachment-68083\" class=\"wp-caption-text\">Risk management plan template <a href=\"https:\/\/www.projectmanager.com\/templates\/risk-management-plan-template\">Free download<\/a><\/figcaption><\/figure>\n<h2>What Should Be Included in a Risk Management Plan?<\/h2>\n<p>Making a risk management plan is essential for identifying, analyzing and responding to risks that could affect a project\u2019s success. For a risk management plan to be effective, it should include certain key components. A risk management plan usually includes the following sections.<\/p>\n<h3>Risk Management Methodology<\/h3>\n<p>A risk management methodology defines the structured approach a project uses to identify, analyze, respond to and monitor risks. It establishes the tools, techniques and data sources used to evaluate uncertainty, assess probability and impact, and determine appropriate responses.<\/p>\n<p>In a risk management plan, the risk management methodology section explains how risk activities will be performed on the project. It documents the tools, techniques and documentation to be used for risk identification, analysis and prioritization so stakeholders understand how risks are managed. This section ensures risk management is repeatable, aligned with organizational standards and applied consistently throughout the project life cycle execution.<\/p>\n<h3>Risk Identification Techniques<\/h3>\n<p>Risk identification techniques are systematic methods used to recognize potential problems, uncertainties, or threats that could impact a project\u2019s objectives. By proactively identifying risks, project teams can assess their likelihood and impact, prioritize responses and develop mitigation strategies. These techniques help ensure that risks are managed before they escalate, supporting smoother <a href=\"https:\/\/www.projectmanager.com\/blog\/project-execution\">project execution<\/a> and informed decision-making.<\/p>\n<ul>\n<li data-start=\"527\" data-end=\"681\"><strong data-start=\"527\" data-end=\"545\">Brainstorming:<\/strong> Collaborative sessions where team members generate a list of potential risks, encouraging diverse perspectives and creative thinking.<\/li>\n<li data-start=\"684\" data-end=\"845\"><strong data-start=\"684\" data-end=\"705\">Delphi Technique:<\/strong> Experts anonymously provide risk input in multiple rounds, refining ideas until consensus is reached, reducing bias from dominant voices.<\/li>\n<li data-start=\"848\" data-end=\"988\"><strong data-start=\"848\" data-end=\"866\">SWOT Analysis:<\/strong> Evaluates internal strengths and weaknesses and external opportunities and threats to identify areas of potential risk.<\/li>\n<li data-start=\"991\" data-end=\"1128\"><strong data-start=\"991\" data-end=\"1006\">Checklists:<\/strong> Uses predefined lists of common risks based on previous projects or industry standards to ensure nothing is overlooked.<\/li>\n<li data-start=\"1131\" data-end=\"1286\" data-is-last-node=\"\"><a href=\"https:\/\/www.projectmanager.com\/blog\/root-cause-analysis-guide\"><strong data-start=\"1131\" data-end=\"1155\">Root Cause Analysis:<\/strong><\/a> Investigates underlying causes of potential problems, identifying risks by understanding what could trigger failures or obstacles.<\/li>\n<\/ul>\n<h3>Risk Scoring and Prioritization Tools<\/h3>\n<p>Risk scoring assigns numerical or qualitative values to identified risks based on their probability of occurrence and potential impact. Risk prioritization then ranks these risks to determine which require the most immediate attention and resources. In a PMI-aligned risk management plan, scoring and prioritization are critical for <a href=\"https:\/\/www.projectmanager.com\/blog\/mitigate-risk-project\">focusing mitigation<\/a> and response strategies on high-priority risks.<\/p>\n<p>By systematically evaluating each risk, project teams can allocate resources efficiently, monitor critical threats and integrate response actions into project schedules, budgets and decision-making, ensuring alignment with <a href=\"https:\/\/www.projectmanager.com\/blog\/project-management-body-of-knowledge-pmbok-a-quick-guide\">PMBOK<\/a> principles for proactive and structured risk management.<\/p>\n<p><a href=\"\/\">ProjectManager<\/a> makes it seamless to understand risks and how they can impact your project. Our built-in risk management features enable you to identify risks, set a priority, assign an owner and more. Use it to take action to keep your projects on track. Get started by taking a free 30-day trial, no credit card required.<\/p>\n<a href=\"https:\/\/www.projectmanager.com\/software\/risk-management\"><img loading=\"lazy\" decoding=\"async\" class=\"aligncenter wp-image-64227 size-full\" src=\"\/wp-content\/uploads\/2021\/09\/Risks-New-Risk-Card.jpg\" alt=\"Risk management in ProjectManager\" width=\"1315\" height=\"982\" srcset=\"\/wp-content\/uploads\/2021\/09\/Risks-New-Risk-Card.jpg 1315w, \/wp-content\/uploads\/2021\/09\/Risks-New-Risk-Card-600x448.jpg 600w, \/wp-content\/uploads\/2021\/09\/Risks-New-Risk-Card-300x224.jpg 300w, \/wp-content\/uploads\/2021\/09\/Risks-New-Risk-Card-768x574.jpg 768w, \/wp-content\/uploads\/2021\/09\/Risks-New-Risk-Card-450x336.jpg 450w\" sizes=\"auto, (max-width: 1315px) 100vw, 1315px\" \/><\/a>\n<h3>Organizational Risk Tolerance or Risk Appetite<\/h3>\n<p>Organizational risk tolerance, or risk appetite, defines the level and type of risk an organization is willing to accept in pursuit of its objectives. In a risk management plan, understanding this threshold guides decision-making, prioritizes risk responses and ensures that mitigation strategies align with the organization\u2019s strategic goals, helping project teams manage uncertainties without exceeding acceptable risk levels.<\/p>\n<ul>\n<li><strong>Risk acceptance criteria:<\/strong> Define when a risk can be accepted without further mitigation, ensuring decisions stay within organizational tolerance, align with project objectives and are formally documented.<\/li>\n<li><strong>Risk exposure thresholds:<\/strong> Set the maximum impact or likelihood a risk can reach before action is required, helping teams prioritize responses, <a href=\"https:\/\/www.projectmanager.com\/blog\/resource-allocation\">allocate resources effectively<\/a> and stay aligned with risk appetite.<\/li>\n<\/ul>\n<h3>Risk Reporting Guidelines and Documentation<\/h3>\n<p>Risk reporting is the systematic process of communicating identified risks, their status, potential impact and mitigation measures to project stakeholders. Within a risk management plan, risk reporting ensures transparency, enables informed decision-making, supports proactive risk response and tracks the effectiveness of mitigation strategies throughout the project lifecycle, keeping stakeholders aligned and facilitating timely escalation of critical issues.<\/p>\n<p>Popular risk reporting documents include:<\/p>\n<ul>\n<li><strong>Risk Register:<\/strong> A centralized document listing all identified risks, their probability, impact, mitigation strategies and ownership, updated throughout the project to track risk status.<\/li>\n<li data-start=\"733\" data-end=\"913\"><strong data-start=\"733\" data-end=\"747\">Issue Log:<\/strong> Tracks current problems affecting the project, linking them to identified risks, documenting resolutions and ensuring accountability and timely corrective action.<\/li>\n<li data-start=\"916\" data-end=\"1091\"><strong data-start=\"916\" data-end=\"929\">RAID Log:<\/strong> Captures Risks, Assumptions, Issues and Dependencies, providing a holistic view of project uncertainties and facilitating structured reporting and management.<\/li>\n<li data-start=\"1094\" data-end=\"1251\"><strong data-start=\"1094\" data-end=\"1112\">Risk Heat Map:<\/strong> Visual representation of risks by probability and impact, helping stakeholders quickly identify high-priority risks requiring attention.<\/li>\n<li data-start=\"1254\" data-end=\"1429\" data-is-last-node=\"\"><strong data-start=\"1254\" data-end=\"1277\">Risk Status Report:<\/strong> Periodic report summarizing active risks, progress on mitigation actions, changes in risk exposure and emerging threats to keep stakeholders informed.<\/li>\n<\/ul>\n<p><strong>Related:<\/strong>\u00a0<a href=\"https:\/\/www.projectmanager.com\/blog\/free-risk-management-templates\">12 Free Risk Management Templates for Excel &amp; Word<\/a><\/p>\n<h3>Risk Register<\/h3>\n<p>A <a href=\"https:\/\/www.projectmanager.com\/blog\/guide-using-risk-register\">risk register<\/a> is a chart to document the risk identification information. It serves as a centralized repository that captures and tracks all identified risks throughout the project life cycle. This provides a comprehensive overview, systematic tracking, prioritization of critical risks, stakeholder engagement and more.<\/p>\n<figure id=\"attachment_64093\" aria-describedby=\"caption-attachment-64093\" style=\"width: 1398px\" class=\"wp-caption aligncenter\"><a href=\"https:\/\/www.projectmanager.com\/templates\/risk-tracking-template\"><img loading=\"lazy\" decoding=\"async\" class=\"wp-image-64093 size-full\" src=\"\/wp-content\/uploads\/2022\/09\/Risk-Tracking-Screenshot.webp\" alt=\"Risk tracking template Excel\" width=\"1398\" height=\"611\" srcset=\"\/wp-content\/uploads\/2022\/09\/Risk-Tracking-Screenshot.webp 1398w, \/wp-content\/uploads\/2022\/09\/Risk-Tracking-Screenshot-600x262.webp 600w, \/wp-content\/uploads\/2022\/09\/Risk-Tracking-Screenshot-300x131.webp 300w, \/wp-content\/uploads\/2022\/09\/Risk-Tracking-Screenshot-768x336.webp 768w, \/wp-content\/uploads\/2022\/09\/Risk-Tracking-Screenshot-450x197.webp 450w\" sizes=\"auto, (max-width: 1398px) 100vw, 1398px\" \/><\/a><figcaption id=\"caption-attachment-64093\" class=\"wp-caption-text\">Risk tracking template <a href=\"https:\/\/www.projectmanager.com\/templates\/risk-tracking-template\">Free download<\/a><\/figcaption><\/figure>\n<h3>Risk Response Plan<\/h3>\n<p>A <a href=\"https:\/\/www.projectmanager.com\/blog\/risk-response-plan-strategies-tips\">risk response plan<\/a> is a project management document that explains the risk mitigation strategies that will be employed. Its purpose is to proactively manage uncertainties, reduce potential impacts on project goals, and ensure preparedness. By assigning responsibilities, defining timelines, and outlining procedures, the plan provides a clear, structured approach to maintaining control and keeping the project on track.<\/p>\n<p>This plan enables project teams to anticipate and address potential issues before they escalate, reducing delays, cost overruns, and quality problems. It ensures that risks are managed systematically rather than reactively, improves decision-making, aligns stakeholder expectations, and provides a documented framework for accountability. Ultimately, it helps protect project objectives and supports smoother, more predictable project execution.<\/p>\n<ul>\n<li><strong>Risk mitigation strategies:<\/strong> Proactive actions designed to reduce the likelihood or impact of identified risks. In a risk management plan, these strategies help minimize disruptions, protect project objectives, guide resource allocation, support contingency planning and provide structured responses to uncertainty before risks escalate.<\/li>\n<li><strong>Risk management roles and responsibilities:<\/strong> Define who identifies, owns, monitors and responds to risks throughout the project. Clearly assigned responsibilities\u2014from the project manager and risk owners to stakeholders and support teams\u2014ensure accountability, consistent risk oversight and effective execution of risk response actions.<\/li>\n<\/ul>\n<h3>Risk Management Budget<\/h3>\n<p>Have a section to identify the funds required to perform risk management activities. This financial plan will allocate resources specifically for identifying, assessing and managing risks within a project. The budget ensures there&#8217;s enough funding available to implement risk management strategies and mitigate negative impacts on project objectives.<\/p>\n<h3>Risk Breakdown Structure<\/h3>\n<p>This is a chart that identifies risk categories and the hierarchical structure of project risks. It\u00a0provides a structured risk identification, which makes it easier to analyze and manage risks. The <a href=\"https:\/\/www.projectmanager.com\/blog\/risk-breakdown-structure\">risk breakdown structure<\/a> also provides clear definitions and descriptions of risks at various levels, which helps the team to understand the nature and source of each risk. Risks can be prioritized more effectively, too.<\/p>\n<h3>Risk Assessment Matrix<\/h3>\n<p>A <a href=\"https:\/\/www.projectmanager.com\/blog\/risk-assessment-matrix-for-qualitative-analysis\">risk assessment matrix<\/a> allows teams to analyze the likelihood and the impact of project risks so they can prioritize them.<\/p>\n<p>Using a risk assessment matrix provides a visual representation of the relationship between the likelihood of risks occurring and their potential impact. It helps teams to focus on critical risks by categorizing them into different levels. The risk assessment matrix also facilitates communication to ensure everyone is aligned on risk prioritization.<\/p>\n<figure id=\"attachment_61446\" aria-describedby=\"caption-attachment-61446\" style=\"width: 675px\" class=\"wp-caption aligncenter\"><a href=\"https:\/\/www.projectmanager.com\/templates\/risk-matrix-template-for-excel\"><img loading=\"lazy\" decoding=\"async\" class=\"wp-image-61446 size-full\" src=\"\/wp-content\/uploads\/2021\/09\/Risk-Matrix-Screenshot.jpg\" alt=\"Risk matrix assessment template\" width=\"675\" height=\"657\" srcset=\"\/wp-content\/uploads\/2021\/09\/Risk-Matrix-Screenshot.jpg 675w, \/wp-content\/uploads\/2021\/09\/Risk-Matrix-Screenshot-600x584.jpg 600w, \/wp-content\/uploads\/2021\/09\/Risk-Matrix-Screenshot-300x292.jpg 300w, \/wp-content\/uploads\/2021\/09\/Risk-Matrix-Screenshot-450x438.jpg 450w\" sizes=\"auto, (max-width: 675px) 100vw, 675px\" \/><\/a><figcaption id=\"caption-attachment-61446\" class=\"wp-caption-text\">Risk matrix assessment template <a href=\"https:\/\/www.projectmanager.com\/templates\/risk-matrix-template-for-excel\">Free download<\/a><\/figcaption><\/figure>\n<h2>How to Write a Risk Management Plan<\/h2>\n<p>For every web design and development project,<a href=\"\/guides\/construction-project-management\"> construction project<\/a> or product design, there will be risks. That\u2019s the nature of project management. But that\u2019s also why it\u2019s always best to get ahead of them as much as possible by developing a risk management plan. We&#8217;ve outlined the steps to make a risk management plan below.<\/p>\n<h3>1. Risk Planning<\/h3>\n<p>You can&#8217;t create a risk management plan without understanding the overall risk planning approach. In other words, what methodologies, roles, responsibilities, budget allocation and timing will be used throughout the project life cycle? This information will set the foundation for the plan itself.<\/p>\n<h3>2. Risk Identification<\/h3>\n<p>Risk identification occurs at the beginning of the project planning phase, as well as throughout the project life cycle. While many risks are considered \u201cknown risks,\u201d others might require additional research.<\/p>\n<p>Create a <a href=\"\/blog\/risk-breakdown-structure\">risk breakdown structure<\/a> to identify project risks and classify them into risk categories. You can do this by interviewing all project stakeholders and industry experts. Many project risks can be divided into risk categories, like technical or organizational, and listed out by specific sub-categories like technology, interfaces, performance, logistics, budget, etc. Additionally, create a risk register to share with everyone interviewed for a centralized location of all known risks revealed during the identification phase.<\/p>\n<h3>3. Risk Assessment<\/h3>\n<p>In this next phase, review the qualitative and quantitative impact of the risk\u2014like the likelihood of the risk occurring versus the impact it would have on the project\u2014and map that out into <a href=\"\/blog\/risk-assessment-matrix-for-qualitative-analysis\">a risk assessment matrix<\/a><\/p>\n<p>First, you\u2019ll do this by assigning the risk likelihood a score from low probability to high probability. Then, map out the risk impact from low to medium to high and assign each a score. This provides an idea of how likely the risk is to impact project success as well as how urgent the response will need to be.<\/p>\n<p>To make it efficient for all risk management team members and project stakeholders to understand the risk assessment matrix, assign an overall risk score by multiplying the impact level score by the risk probability score.<\/p>\n<h3>4. Risk Mitigation: Create a Risk Response Plan<\/h3>\n<p>A risk response is the <a href=\"\/training\/make-action-plan\">action plan<\/a> taken to mitigate project risks when they occur. The risk response plan includes risk mitigation strategies to mitigate the impact of project risks. Doing this usually comes with a price\u2014at the expense of your time or your budget. So you\u2019ll want to allocate resources, time and money for your risk management needs before creating the risk management plan.<\/p>\n<h3>5. Control &amp; Monitor the Risk<\/h3>\n<p>As soon as the risk mitigation response has been established, it&#8217;s time to actively control any risks. In other words, how will the responses be executed, evaluated for effectiveness and altered as project conditions or risk exposure change?<\/p>\n<h3>6. Assign Risk Owners<\/h3>\n<p>Next, assign a risk owner to each project risk. Those risk owners become accountable for monitoring the risks assigned to them and supervising the execution of the risk response if needed.<\/p>\n<p><strong>Related:<\/strong> <a href=\"\/templates\/risk-tracking-template\">Risk Tracking Template<\/a><\/p>\n<p>When creating the risk register and risk assessment matrix, list out the risk owners; that way, no one is confused as to who will need to implement the risk response strategies once the project risks occur, and each risk owner can take immediate action.<\/p>\n<p>Be sure to record the exact risk response for each project risk with a risk register and have the risk response plan approved by all stakeholders before implementation. That way, there&#8217;s a record of the issue and the resolution to review once the project is finalized.<\/p>\n<a class=\"trapdoor\" href=\"https:\/\/learn.projectmanager.com\/pm-101-ebook\" target=\"_blank\" rel=\"noopener\"><img loading=\"lazy\" decoding=\"async\" class=\"aligncenter wp-image-73861 size-full\" src=\"\/wp-content\/uploads\/2025\/02\/PM-101-eBook-banner-ad.jpg\" alt=\"PM 101 eBook banner-ad\" width=\"2021\" height=\"521\" srcset=\"\/wp-content\/uploads\/2025\/02\/PM-101-eBook-banner-ad.jpg 2021w, \/wp-content\/uploads\/2025\/02\/PM-101-eBook-banner-ad-600x155.jpg 600w, \/wp-content\/uploads\/2025\/02\/PM-101-eBook-banner-ad-1600x412.jpg 1600w, \/wp-content\/uploads\/2025\/02\/PM-101-eBook-banner-ad-300x77.jpg 300w, \/wp-content\/uploads\/2025\/02\/PM-101-eBook-banner-ad-768x198.jpg 768w, \/wp-content\/uploads\/2025\/02\/PM-101-eBook-banner-ad-1536x396.jpg 1536w, \/wp-content\/uploads\/2025\/02\/PM-101-eBook-banner-ad-450x116.jpg 450w\" sizes=\"auto, (max-width: 2021px) 100vw, 2021px\" \/><\/a>\n<h3>7. Understand Your Triggers<\/h3>\n<p>This can happen with or without a risk already having impacted the project, especially during <a href=\"https:\/\/www.projectmanager.com\/blog\/milestones-project-management\">project milestones<\/a> as a means of reviewing project progress. If they have, consider reclassifying those existing risks.<\/p>\n<p>Even if those triggers haven\u2019t been met, it\u2019s best to come up with a backup plan as the project progresses\u2014maybe the conditions for a certain risk won\u2019t exist after a certain point has been reached in the project.<\/p>\n<h3>8. Make a Backup Plan<\/h3>\n<p>Consider your risk register and risk assessment matrix a living document. Project risks can change in classification at any point, and because of that, come up with a contingency plan as part of the process.<\/p>\n<p><a href=\"https:\/\/www.projectmanager.com\/blog\/contingency-plan\">Contingency planning<\/a> includes discovering new risks during project milestones and reevaluating existing risks to see if any conditions for those risks have been met. Any reclassification of a risk means adjusting your contingency plan.<\/p>\n<h3>9. Measure Your Risk Threshold<\/h3>\n<p>Measuring your risk threshold is all about discovering which risk is too high and consulting with project stakeholders to consider whether or not it\u2019s worth it to continue the project, worth it whether in time, money or <a href=\"\/blog\/project-scope\">scope<\/a>.<\/p>\n<p>Here\u2019s how the risk threshold is typically determined: consider your risks that have a score of \u201cvery high\u201d, or more than a few \u201chigh\u201d scores, and consult with your leadership team and project stakeholders to determine if the project itself may be at risk of failure. Project risks that require additional consultation are risks that have passed the risk threshold.<\/p>\n<p>To keep a close eye on risks as they arise in the project, use project management software. ProjectManager has <a href=\"\/software\/dashboards\">real-time dashboards<\/a> embedded in our tool, unlike other software that requires teams to manually build them. We automatically calculate the health of projects, checking if teams are on time or running behind. Get a high-level view of how much you&#8217;re spending, progress and more. The quicker the risk is identified, the faster you can resolve it.<\/p>\n<a href=\"\/software\/dashboard\"><img loading=\"lazy\" decoding=\"async\" class=\"aligncenter wp-image-77489 size-full\" src=\"\/wp-content\/uploads\/2025\/10\/AI-Project-Insights-Dashboard-Edited-Lightmode.png\" alt=\"Dashboard in ProjectManager\" width=\"1918\" height=\"908\" srcset=\"\/wp-content\/uploads\/2025\/10\/AI-Project-Insights-Dashboard-Edited-Lightmode.png 1918w, \/wp-content\/uploads\/2025\/10\/AI-Project-Insights-Dashboard-Edited-Lightmode-600x284.png 600w, \/wp-content\/uploads\/2025\/10\/AI-Project-Insights-Dashboard-Edited-Lightmode-1600x757.png 1600w, \/wp-content\/uploads\/2025\/10\/AI-Project-Insights-Dashboard-Edited-Lightmode-300x142.png 300w, \/wp-content\/uploads\/2025\/10\/AI-Project-Insights-Dashboard-Edited-Lightmode-768x364.png 768w, \/wp-content\/uploads\/2025\/10\/AI-Project-Insights-Dashboard-Edited-Lightmode-1536x727.png 1536w, \/wp-content\/uploads\/2025\/10\/AI-Project-Insights-Dashboard-Edited-Lightmode-450x213.png 450w\" sizes=\"auto, (max-width: 1918px) 100vw, 1918px\" \/><\/a>\n<h3>10. Keep Stakeholders Informed<\/h3>\n<p>Stakeholders should always be aware of how risks are progressing and being handled throughout the project. The plan should note how risks are reported, escalated and communicated as needed.<\/p>\n<h2>Risk Management Plan Example<\/h2>\n<p>This risk management plan defines the approach used to identify, analyze, prioritize and manage risks for a multi-story residential parking garage construction project. The plan establishes consistent methods and thresholds to support proactive decision-making throughout the project lifecycle.<\/p>\n<h3>Risk Management Methodology<\/h3>\n<p>The risk management methodology defines how risks will be identified, assessed, prioritized and monitored throughout the project. It establishes a structured, repeatable process to ensure risks are managed consistently and aligned with project objectives related to safety, schedule, cost and quality.<\/p>\n<table>\n<tbody>\n<tr>\n<td style=\"border: 1px solid gray;\"><b>Methodology Step<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Description<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Tools and Techniques<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Responsible Party<\/b><\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">Risk identification<\/td>\n<td style=\"border: 1px solid gray;\">Systematically identify potential project risks<\/td>\n<td style=\"border: 1px solid gray;\">Workshops, checklists, site reviews<\/td>\n<td style=\"border: 1px solid gray;\">Project manager<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">Qualitative analysis<\/td>\n<td style=\"border: 1px solid gray;\">Assess likelihood and impact of identified risks<\/td>\n<td style=\"border: 1px solid gray;\">Probability\u2013impact matrix<\/td>\n<td style=\"border: 1px solid gray;\">Project team<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">Risk prioritization<\/td>\n<td style=\"border: 1px solid gray;\">Rank risks based on exposure<\/td>\n<td style=\"border: 1px solid gray;\">Risk scoring model<\/td>\n<td style=\"border: 1px solid gray;\">Project manager<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">Risk monitoring<\/td>\n<td style=\"border: 1px solid gray;\">Track risks and response effectiveness<\/td>\n<td style=\"border: 1px solid gray;\">Risk register updates, reviews<\/td>\n<td style=\"border: 1px solid gray;\">Project manager<\/td>\n<\/tr>\n<\/tbody>\n<\/table>\n<h3>Risk Identification Techniques<\/h3>\n<p>Risk identification techniques are used to proactively uncover potential threats that may impact <a href=\"https:\/\/www.projectmanager.com\/training\/how-to-write-effective-project-objectives-every-time\">project objectives.<\/a> These techniques draw on historical data, expert judgment and field-level observations to ensure comprehensive coverage.<\/p>\n<table>\n<tbody>\n<tr>\n<td style=\"border: 1px solid gray;\"><b>Technique<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Description<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Application<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Participants<\/b><\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">Risk workshops<\/td>\n<td style=\"border: 1px solid gray;\">Facilitated sessions to identify risks collaboratively<\/td>\n<td style=\"border: 1px solid gray;\">Planning and early execution<\/td>\n<td style=\"border: 1px solid gray;\">Project team, subcontractors<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">Historical data review<\/td>\n<td style=\"border: 1px solid gray;\">Analyze risks from similar past projects<\/td>\n<td style=\"border: 1px solid gray;\">Preconstruction phase<\/td>\n<td style=\"border: 1px solid gray;\">Project manager<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">Site inspections<\/td>\n<td style=\"border: 1px solid gray;\">Identify risks related to site conditions<\/td>\n<td style=\"border: 1px solid gray;\">Throughout construction<\/td>\n<td style=\"border: 1px solid gray;\">Site supervisor<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">Expert judgment<\/td>\n<td style=\"border: 1px solid gray;\">Input from engineers and specialists<\/td>\n<td style=\"border: 1px solid gray;\">Design and execution phases<\/td>\n<td style=\"border: 1px solid gray;\">Design consultants<\/td>\n<\/tr>\n<\/tbody>\n<\/table>\n<h3>Risk Scoring and Prioritization<\/h3>\n<p>Risk scoring and prioritization evaluate identified risks based on their probability of occurrence and potential impact on project objectives. The resulting risk exposure score is used to rank risks and determine response priority.<\/p>\n<table>\n<tbody>\n<tr>\n<td style=\"border: 1px solid gray;\"><b>Risk ID<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Risk Description<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Probability<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Impact<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Risk Score<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Priority Level<\/b><\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">R-01<\/td>\n<td style=\"border: 1px solid gray;\">Unexpected subsurface conditions<\/td>\n<td style=\"border: 1px solid gray;\">High<\/td>\n<td style=\"border: 1px solid gray;\">High<\/td>\n<td style=\"border: 1px solid gray;\">9<\/td>\n<td style=\"border: 1px solid gray;\">Critical<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">R-02<\/td>\n<td style=\"border: 1px solid gray;\">Concrete supply delays<\/td>\n<td style=\"border: 1px solid gray;\">Medium<\/td>\n<td style=\"border: 1px solid gray;\">High<\/td>\n<td style=\"border: 1px solid gray;\">6<\/td>\n<td style=\"border: 1px solid gray;\">High<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">R-03<\/td>\n<td style=\"border: 1px solid gray;\">Weather-related work stoppages<\/td>\n<td style=\"border: 1px solid gray;\">Medium<\/td>\n<td style=\"border: 1px solid gray;\">Medium<\/td>\n<td style=\"border: 1px solid gray;\">4<\/td>\n<td style=\"border: 1px solid gray;\">Moderate<\/td>\n<\/tr>\n<\/tbody>\n<\/table>\n<h3>Organizational Risk Tolerance<\/h3>\n<p>Organizational risk tolerance defines the level of risk exposure the organization is willing to accept in pursuit of project objectives. These thresholds guide decision-making, escalation and the selection of risk response strategies.<\/p>\n<table>\n<tbody>\n<tr>\n<td style=\"border: 1px solid gray;\"><b>Risk Category<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Risk Acceptance Criteria<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Risk Exposure Threshold<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Required Action<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Escalation Authority<\/b><\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">Safety<\/td>\n<td style=\"border: 1px solid gray;\">No tolerance for high-severity safety risks<\/td>\n<td style=\"border: 1px solid gray;\">Score \u2265 6<\/td>\n<td style=\"border: 1px solid gray;\">Immediate mitigation required<\/td>\n<td style=\"border: 1px solid gray;\">Project sponsor<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">Schedule<\/td>\n<td style=\"border: 1px solid gray;\">Minor delays acceptable if recoverable<\/td>\n<td style=\"border: 1px solid gray;\">Score \u2265 5<\/td>\n<td style=\"border: 1px solid gray;\">Mitigation and resequencing<\/td>\n<td style=\"border: 1px solid gray;\">Project manager<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">Cost<\/td>\n<td style=\"border: 1px solid gray;\">Cost increases limited to contingency<\/td>\n<td style=\"border: 1px solid gray;\">Score \u2265 5<\/td>\n<td style=\"border: 1px solid gray;\">Management approval required<\/td>\n<td style=\"border: 1px solid gray;\">Finance lead<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">Quality<\/td>\n<td style=\"border: 1px solid gray;\">Rework acceptable within standards<\/td>\n<td style=\"border: 1px solid gray;\">Score \u2265 4<\/td>\n<td style=\"border: 1px solid gray;\">Corrective action plan<\/td>\n<td style=\"border: 1px solid gray;\">Project manager<\/td>\n<\/tr>\n<\/tbody>\n<\/table>\n<h3>Risk Register<\/h3>\n<p>The risk register serves as the central repository for all identified project risks. It documents risk descriptions, ownership, priority levels and current status, enabling ongoing monitoring and informed decision-making throughout the project lifecycle.<\/p>\n<table>\n<tbody>\n<tr>\n<td style=\"border: 1px solid gray;\"><b>Risk ID<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Risk Description<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Category<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Risk Score<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Risk Owner<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Status<\/b><\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">R-01<\/td>\n<td style=\"border: 1px solid gray;\">Unexpected subsurface conditions<\/td>\n<td style=\"border: 1px solid gray;\">Technical<\/td>\n<td style=\"border: 1px solid gray;\">9<\/td>\n<td style=\"border: 1px solid gray;\">Project manager<\/td>\n<td style=\"border: 1px solid gray;\">Open<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">R-02<\/td>\n<td style=\"border: 1px solid gray;\">Concrete supply delays<\/td>\n<td style=\"border: 1px solid gray;\">Supply chain<\/td>\n<td style=\"border: 1px solid gray;\">6<\/td>\n<td style=\"border: 1px solid gray;\">Procurement lead<\/td>\n<td style=\"border: 1px solid gray;\">Open<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">R-03<\/td>\n<td style=\"border: 1px solid gray;\">Severe weather impacts on schedule<\/td>\n<td style=\"border: 1px solid gray;\">Environmental<\/td>\n<td style=\"border: 1px solid gray;\">4<\/td>\n<td style=\"border: 1px solid gray;\">Site supervisor<\/td>\n<td style=\"border: 1px solid gray;\">Monitoring<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">R-04<\/td>\n<td style=\"border: 1px solid gray;\">Safety incidents during elevated work<\/td>\n<td style=\"border: 1px solid gray;\">Safety<\/td>\n<td style=\"border: 1px solid gray;\">8<\/td>\n<td style=\"border: 1px solid gray;\">Safety officer<\/td>\n<td style=\"border: 1px solid gray;\">Open<\/td>\n<\/tr>\n<\/tbody>\n<\/table>\n<h3>Risk Response Plan<\/h3>\n<p>The risk response plan defines specific actions to address prioritized risks. Response strategies are selected based on organizational risk tolerance and are assigned to accountable roles responsible for implementation and monitoring.<\/p>\n<table>\n<tbody>\n<tr>\n<td style=\"border: 1px solid gray;\"><b>Risk ID<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Risk Description<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Risk Mitigation Strategy<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Response Type<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Roles and Responsibilities<\/b><\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">R-01<\/td>\n<td style=\"border: 1px solid gray;\">Unexpected subsurface conditions<\/td>\n<td style=\"border: 1px solid gray;\">Conduct early geotechnical surveys and include contingency plans<\/td>\n<td style=\"border: 1px solid gray;\">Mitigate<\/td>\n<td style=\"border: 1px solid gray;\">Project manager coordinates studies and approvals<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">R-02<\/td>\n<td style=\"border: 1px solid gray;\">Concrete supply delays<\/td>\n<td style=\"border: 1px solid gray;\">Prequalify alternate suppliers and place early orders<\/td>\n<td style=\"border: 1px solid gray;\">Mitigate<\/td>\n<td style=\"border: 1px solid gray;\">Procurement lead manages supplier agreements<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">R-03<\/td>\n<td style=\"border: 1px solid gray;\">Severe weather impacts<\/td>\n<td style=\"border: 1px solid gray;\">Build schedule buffers and resequence non-critical work<\/td>\n<td style=\"border: 1px solid gray;\">Accept<\/td>\n<td style=\"border: 1px solid gray;\">Site supervisor adjusts daily work plans<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">R-04<\/td>\n<td style=\"border: 1px solid gray;\">Safety incidents during elevated work<\/td>\n<td style=\"border: 1px solid gray;\">Implement enhanced safety training and inspections<\/td>\n<td style=\"border: 1px solid gray;\">Avoid<\/td>\n<td style=\"border: 1px solid gray;\">Safety officer enforces compliance and reporting<\/td>\n<\/tr>\n<\/tbody>\n<\/table>\n<h3>Risk Management Budget<\/h3>\n<p>The risk management budget allocates funds specifically for risk mitigation and contingency activities. This budget supports proactive risk responses and reduces the likelihood of unplanned cost impacts during execution.<\/p>\n<table>\n<tbody>\n<tr>\n<td style=\"border: 1px solid gray;\"><b>Budget Item<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Purpose<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Estimated Cost (USD)<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>Approval Authority<\/b><\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">Geotechnical investigations<\/td>\n<td style=\"border: 1px solid gray;\">Reduce subsurface condition uncertainty<\/td>\n<td style=\"border: 1px solid gray;\">25,000<\/td>\n<td style=\"border: 1px solid gray;\">Project sponsor<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">Safety training and audits<\/td>\n<td style=\"border: 1px solid gray;\">Prevent high-severity safety incidents<\/td>\n<td style=\"border: 1px solid gray;\">15,000<\/td>\n<td style=\"border: 1px solid gray;\">Safety manager<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\">Schedule contingency<\/td>\n<td style=\"border: 1px solid gray;\">Address weather-related delays<\/td>\n<td style=\"border: 1px solid gray;\">20,000<\/td>\n<td style=\"border: 1px solid gray;\">Project manager<\/td>\n<\/tr>\n<tr>\n<td style=\"border: 1px solid gray;\"><b>Total<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>\u2014<\/b><\/td>\n<td style=\"border: 1px solid gray;\"><b>60,000<\/b><\/td>\n<td style=\"border: 1px solid gray;\">\u2014<\/td>\n<\/tr>\n<\/tbody>\n<\/table>\n<h2>How ProjectManager Can Help Your Risk Management Plan<\/h2>\n<p>A risk management plan is only as good as the risk management features you have to implement and track them. <a href=\"\/\">ProjectManager<\/a> is online project management software that lets you view risks directly in the project menu. You can tag risks as open or closed and even make a risk matrix directly in the software. You get visibility into risks and can track them in real time, sharing and viewing the risk history.<\/p>\n<img loading=\"lazy\" decoding=\"async\" class=\"aligncenter wp-image-69262 size-full\" src=\"\/wp-content\/uploads\/2024\/01\/risk-image-lightmode.png\" alt=\"Risk management popup in ProjectManager\" width=\"2560\" height=\"1411\" srcset=\"\/wp-content\/uploads\/2024\/01\/risk-image-lightmode.png 2560w, \/wp-content\/uploads\/2024\/01\/risk-image-lightmode-600x331.png 600w, \/wp-content\/uploads\/2024\/01\/risk-image-lightmode-1600x882.png 1600w, \/wp-content\/uploads\/2024\/01\/risk-image-lightmode-300x165.png 300w, \/wp-content\/uploads\/2024\/01\/risk-image-lightmode-768x423.png 768w, \/wp-content\/uploads\/2024\/01\/risk-image-lightmode-1536x847.png 1536w, \/wp-content\/uploads\/2024\/01\/risk-image-lightmode-2048x1129.png 2048w, \/wp-content\/uploads\/2024\/01\/risk-image-lightmode-450x248.png 450w\" sizes=\"auto, (max-width: 2560px) 100vw, 2560px\" \/>\n<h3>Tracking &amp; Monitoring Risks in Real Time<\/h3>\n<p>Managing risk is only the start. You must also monitor risk and track it from the point at which you first identified it. Real-time dashboards provide a high-level view of slippage, workload, cost and more. <a href=\"\/software\/reporting\">Customizable reports<\/a> can be shared with stakeholders and filtered to show only what they need to see. Risk tracking has never been easier.<\/p>\n<a href=\"\/software\/reporting\"><img loading=\"lazy\" decoding=\"async\" class=\"aligncenter wp-image-70996 size-full\" src=\"\/wp-content\/uploads\/2024\/06\/Project-portfolio-status-report.png\" alt=\"Screenshot of the project status report in ProjectManager, ideal for risk management\" width=\"2552\" height=\"1397\" srcset=\"\/wp-content\/uploads\/2024\/06\/Project-portfolio-status-report.png 2552w, \/wp-content\/uploads\/2024\/06\/Project-portfolio-status-report-600x328.png 600w, \/wp-content\/uploads\/2024\/06\/Project-portfolio-status-report-1600x876.png 1600w, \/wp-content\/uploads\/2024\/06\/Project-portfolio-status-report-300x164.png 300w, \/wp-content\/uploads\/2024\/06\/Project-portfolio-status-report-768x420.png 768w, \/wp-content\/uploads\/2024\/06\/Project-portfolio-status-report-1536x841.png 1536w, \/wp-content\/uploads\/2024\/06\/Project-portfolio-status-report-2048x1121.png 2048w, \/wp-content\/uploads\/2024\/06\/Project-portfolio-status-report-450x246.png 450w\" sizes=\"auto, (max-width: 2552px) 100vw, 2552px\" \/><\/a>\n<h2>Best Practices for Maintaining Your Risk Management Plan<\/h2>\n<p>Risk management plans only fail in a few ways: incrementally because of insufficient budget, via modeling errors or by ignoring your risks outright.<\/p>\n<p>Your risk management plan is constantly evolving throughout the project life cycle, from beginning to end. So the best practices are to focus on <a href=\"\/blog\/project-monitoring-and-control\">the monitoring phase<\/a> of the risk management plan. Continue to evaluate and reevaluate your risks and their scores, and address risks at every project milestone.<\/p>\n<p><a href=\"https:\/\/www.projectmanager.com\/software\/dashboard\">Project dashboards<\/a> and other risk-tracking features can be a lifesaver for maintaining your risk management plan. Watch the video below to see just how important project management dashboards, live data and project reports can be for keeping projects on track and budget.<\/p>\n<p>In addition to routine risk monitoring, at each milestone, conduct another round of interviews with the same checklist you used at the beginning of the project, and re-interview project stakeholders, risk management team members, customers (if applicable) and industry experts.<\/p>\n<p>Record their answers, adjust the risk register and risk assessment matrix if necessary, and report all relevant updates of your risk management plan to key project stakeholders. This process and level of transparency help identify any new risks to be assessed and show if any previous risks have expired.<\/p>\n<img loading=\"lazy\" decoding=\"async\" width=\"600\" height=\"1079\" class=\"aligncenter size-medium wp-image-71907\" src=\"\/wp-content\/uploads\/2024\/09\/Steps-to-a-risk-management-plan-600x1079.png\" alt=\"Steps to a risk management plan infographic ProjectManager\" srcset=\"\/wp-content\/uploads\/2024\/09\/Steps-to-a-risk-management-plan-600x1079.png 600w, \/wp-content\/uploads\/2024\/09\/Steps-to-a-risk-management-plan-300x539.png 300w, \/wp-content\/uploads\/2024\/09\/Steps-to-a-risk-management-plan-768x1381.png 768w, \/wp-content\/uploads\/2024\/09\/Steps-to-a-risk-management-plan-854x1536.png 854w, \/wp-content\/uploads\/2024\/09\/Steps-to-a-risk-management-plan-450x809.png 450w, \/wp-content\/uploads\/2024\/09\/Steps-to-a-risk-management-plan.png 1080w\" sizes=\"auto, (max-width: 600px) 100vw, 600px\" \/>\n<h2>Related Content<\/h2>\n<ul>\n<li><a href=\"https:\/\/www.projectmanager.com\/es\/plan-de-gestion-de-riesgos\">C\u00f3mo hacer un plan de gesti\u00f3n de riesgos<\/a><\/li>\n<li><a href=\"https:\/\/www.projectmanager.com\/blog\/free-risk-management-templates\">12 Free Risk Management Templates for Excel &amp; Word<\/a><\/li>\n<li><a href=\"https:\/\/www.projectmanager.com\/blog\/risk-assessment-report\">How to Make a Risk Assessment Report (Templates Included)<\/a><\/li>\n<li><a href=\"https:\/\/www.projectmanager.com\/blog\/contractor-risk-management\">A Quick Guide to Contractor Risk &amp; Contractor Risk Management<\/a><\/li>\n<\/ul>\n<p><em>Risks are bound to happen, no matter the project. However, if you have the right tools to better navigate the risk management planning process, you can better mitigate errors. ProjectManager is online project management software that updates in real time, giving you all the latest information on your risks, issues and changes. <a href=\"https:\/\/www.projectmanager.com\/freetrial?edition=d\">Start a free 30-day trial and start managing your risks better.<\/a><\/em><\/p>\n","protected":false},"excerpt":{"rendered":"<p>You identify them, record them, monitor them and plan for them: risks are an inherent part of every project. Some&#8230;<br \/><a class=\"excerpt-read-more button blue\" href=\"https:\/\/www.projectmanager.com\/blog\/risk-management-plan\">Read More<\/a><\/p>\n","protected":false},"author":18,"featured_media":68123,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_yoast_wpseo_meta-robots-noindex":0,"_yoast_wpseo_canonical":"","_yoast_wpseo_opengraph-title":"","_yoast_wpseo_opengraph-description":"","_yoast_wpseo_opengraph-image":"","_yoast_wpseo_twitter-title":"","_yoast_wpseo_twitter-description":"","head_code_insert":"<link rel=\"alternate\" hreflang=\"en-us\" href=\"https:\/\/www.projectmanager.com\/blog\/risk-management-plan\" \/>\r\n<link rel=\"alternate\" hreflang=\"es\" href=\"https:\/\/www.projectmanager.com\/es\/plan-de-gestion-de-riesgos\" \/>\r\n<link rel=\"alternate\" hreflang=\"x-default\" href=\"https:\/\/www.projectmanager.com\/blog\/risk-management-plan\" \/>","footnotes":""},"categories":[195,131,233],"tags":[],"class_list":["post-49088","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-planning","category-blog","category-risk-management"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO Premium plugin v28.3 (Yoast SEO v28.4) - https:\/\/yoast.com\/product\/yoast-seo-premium-wordpress\/ -->\n<title>How to Make a Risk Management Plan (Template Included)<\/title>\n<meta name=\"description\" content=\"Risks lurk in every project\u2014don&#039;t let them get the better of you. Learn how to make an impeccable risk management plan and be prepared.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.projectmanager.com\/blog\/risk-management-plan\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"How to Make a Risk Management Plan (Template Included)\" \/>\n<meta property=\"og:description\" content=\"Risks lurk in every project\u2014don&#039;t let them get the better of you. Learn how to make an impeccable risk management plan and be prepared.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.projectmanager.com\/blog\/risk-management-plan\" \/>\n<meta property=\"og:site_name\" content=\"ProjectManager\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/projectmanage\/\" \/>\n<meta property=\"article:published_time\" content=\"2025-12-15T18:51:26+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2025-12-23T16:52:12+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/www.projectmanager.com\/wp-content\/uploads\/2023\/09\/Risk-management-plan-template.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"940\" \/>\n\t<meta property=\"og:image:height\" content=\"540\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"Peter Landau\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Peter Landau\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"22 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/risk-management-plan#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/risk-management-plan\"},\"author\":{\"name\":\"Peter Landau\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#\\\/schema\\\/person\\\/83c2340d10ac161661864c1938cd4953\"},\"headline\":\"How to Make a Risk Management Plan (Template Included)\",\"datePublished\":\"2025-12-15T18:51:26+00:00\",\"dateModified\":\"2025-12-23T16:52:12+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/risk-management-plan\"},\"wordCount\":4340,\"publisher\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/risk-management-plan#primaryimage\"},\"thumbnailUrl\":\"\\\/wp-content\\\/uploads\\\/2023\\\/09\\\/Risk-management-plan-template.jpg\",\"articleSection\":[\"Planning\",\"Project Management Blog\",\"Risk Management\"],\"inLanguage\":\"en-US\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/risk-management-plan\",\"url\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/risk-management-plan\",\"name\":\"How to Make a Risk Management Plan (Template Included)\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/risk-management-plan#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/risk-management-plan#primaryimage\"},\"thumbnailUrl\":\"\\\/wp-content\\\/uploads\\\/2023\\\/09\\\/Risk-management-plan-template.jpg\",\"datePublished\":\"2025-12-15T18:51:26+00:00\",\"dateModified\":\"2025-12-23T16:52:12+00:00\",\"description\":\"Risks lurk in every project\u2014don't let them get the better of you. Learn how to make an impeccable risk management plan and be prepared.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/risk-management-plan#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/risk-management-plan\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/risk-management-plan#primaryimage\",\"url\":\"\\\/wp-content\\\/uploads\\\/2023\\\/09\\\/Risk-management-plan-template.jpg\",\"contentUrl\":\"\\\/wp-content\\\/uploads\\\/2023\\\/09\\\/Risk-management-plan-template.jpg\",\"width\":940,\"height\":540,\"caption\":\"Risk Management Plan Template\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/risk-management-plan#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/www.projectmanager.com\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"How to Make a Risk Management Plan (Template Included)\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#website\",\"url\":\"https:\\\/\\\/www.projectmanager.com\\\/\",\"name\":\"ProjectManager\",\"description\":\"The Best Project Management Software for Managing your Projects\",\"publisher\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/www.projectmanager.com\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#organization\",\"name\":\"ProjectManager\",\"url\":\"https:\\\/\\\/www.projectmanager.com\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"\\\/wp-content\\\/uploads\\\/2026\\\/06\\\/ProjectManager-Logo-for-Website.png\",\"contentUrl\":\"\\\/wp-content\\\/uploads\\\/2026\\\/06\\\/ProjectManager-Logo-for-Website.png\",\"width\":696,\"height\":696,\"caption\":\"ProjectManager\"},\"image\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#\\\/schema\\\/logo\\\/image\\\/\"},\"sameAs\":[\"https:\\\/\\\/www.facebook.com\\\/projectmanage\\\/\",\"https:\\\/\\\/www.linkedin.com\\\/company\\\/projectmanager.com\\\/\",\"https:\\\/\\\/www.youtube.com\\\/user\\\/projectmanagervideos\",\"https:\\\/\\\/en.wikipedia.org\\\/wiki\\\/ProjectManager.com\"],\"description\":\"ProjectManager is a project and portfolio management software that offers online project management tools like Gantt charts, dashboards, kanban boards, task management features and more. With advanced planning and scheduling, automated cost and time tracking, risk analysis and resource management, our platform ensures flawless execution for construction, manufacturing and professional services teams, while providing unbeatable insights at every stage.\",\"legalName\":\"ProjectManager.com, Inc.\",\"foundingDate\":\"2008-01-01\",\"numberOfEmployees\":{\"@type\":\"QuantitativeValue\",\"minValue\":\"11\",\"maxValue\":\"50\"}},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#\\\/schema\\\/person\\\/83c2340d10ac161661864c1938cd4953\",\"name\":\"Peter Landau\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/7521970efa63d95fa368e8426d2b1e51db76ddf997de4e0377dc781de5d97489?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/7521970efa63d95fa368e8426d2b1e51db76ddf997de4e0377dc781de5d97489?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/7521970efa63d95fa368e8426d2b1e51db76ddf997de4e0377dc781de5d97489?s=96&d=mm&r=g\",\"caption\":\"Peter Landau\"},\"description\":\"Peter is the Content Editor at ProjectManager.com. He has worked as a writer and editor on print, digital and mobile platforms for both consumer and trade publications.\",\"sameAs\":[\"https:\\\/\\\/pmargo.wpengine.com\",\"https:\\\/\\\/www.linkedin.com\\\/pub\\\/peter-landau\\\/3\\\/572\\\/12\"],\"knowsAbout\":[\"Project management\",\"Project planning\",\"Blogs\"],\"knowsLanguage\":[\"English\"],\"jobTitle\":\"Project Management Expert Writer\",\"worksFor\":\"ProjectManager.com\",\"url\":\"https:\\\/\\\/www.projectmanager.com\\\/author\\\/peterlandau\"}]}<\/script>\n<!-- \/ Yoast SEO Premium plugin. -->","yoast_head_json":{"title":"How to Make a Risk Management Plan (Template Included)","description":"Risks lurk in every project\u2014don't let them get the better of you. Learn how to make an impeccable risk management plan and be prepared.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.projectmanager.com\/blog\/risk-management-plan","og_locale":"en_US","og_type":"article","og_title":"How to Make a Risk Management Plan (Template Included)","og_description":"Risks lurk in every project\u2014don't let them get the better of you. Learn how to make an impeccable risk management plan and be prepared.","og_url":"https:\/\/www.projectmanager.com\/blog\/risk-management-plan","og_site_name":"ProjectManager","article_publisher":"https:\/\/www.facebook.com\/projectmanage\/","article_published_time":"2025-12-15T18:51:26+00:00","article_modified_time":"2025-12-23T16:52:12+00:00","og_image":[{"width":940,"height":540,"url":"https:\/\/www.projectmanager.com\/wp-content\/uploads\/2023\/09\/Risk-management-plan-template.jpg","type":"image\/jpeg"}],"author":"Peter Landau","twitter_card":"summary_large_image","twitter_misc":{"Written by":"Peter Landau","Est. reading time":"22 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/www.projectmanager.com\/blog\/risk-management-plan#article","isPartOf":{"@id":"https:\/\/www.projectmanager.com\/blog\/risk-management-plan"},"author":{"name":"Peter Landau","@id":"https:\/\/www.projectmanager.com\/#\/schema\/person\/83c2340d10ac161661864c1938cd4953"},"headline":"How to Make a Risk Management Plan (Template Included)","datePublished":"2025-12-15T18:51:26+00:00","dateModified":"2025-12-23T16:52:12+00:00","mainEntityOfPage":{"@id":"https:\/\/www.projectmanager.com\/blog\/risk-management-plan"},"wordCount":4340,"publisher":{"@id":"https:\/\/www.projectmanager.com\/#organization"},"image":{"@id":"https:\/\/www.projectmanager.com\/blog\/risk-management-plan#primaryimage"},"thumbnailUrl":"\/wp-content\/uploads\/2023\/09\/Risk-management-plan-template.jpg","articleSection":["Planning","Project Management Blog","Risk Management"],"inLanguage":"en-US"},{"@type":"WebPage","@id":"https:\/\/www.projectmanager.com\/blog\/risk-management-plan","url":"https:\/\/www.projectmanager.com\/blog\/risk-management-plan","name":"How to Make a Risk Management Plan (Template Included)","isPartOf":{"@id":"https:\/\/www.projectmanager.com\/#website"},"primaryImageOfPage":{"@id":"https:\/\/www.projectmanager.com\/blog\/risk-management-plan#primaryimage"},"image":{"@id":"https:\/\/www.projectmanager.com\/blog\/risk-management-plan#primaryimage"},"thumbnailUrl":"\/wp-content\/uploads\/2023\/09\/Risk-management-plan-template.jpg","datePublished":"2025-12-15T18:51:26+00:00","dateModified":"2025-12-23T16:52:12+00:00","description":"Risks lurk in every project\u2014don't let them get the better of you. Learn how to make an impeccable risk management plan and be prepared.","breadcrumb":{"@id":"https:\/\/www.projectmanager.com\/blog\/risk-management-plan#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.projectmanager.com\/blog\/risk-management-plan"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.projectmanager.com\/blog\/risk-management-plan#primaryimage","url":"\/wp-content\/uploads\/2023\/09\/Risk-management-plan-template.jpg","contentUrl":"\/wp-content\/uploads\/2023\/09\/Risk-management-plan-template.jpg","width":940,"height":540,"caption":"Risk Management Plan Template"},{"@type":"BreadcrumbList","@id":"https:\/\/www.projectmanager.com\/blog\/risk-management-plan#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/www.projectmanager.com\/"},{"@type":"ListItem","position":2,"name":"How to Make a Risk Management Plan (Template Included)"}]},{"@type":"WebSite","@id":"https:\/\/www.projectmanager.com\/#website","url":"https:\/\/www.projectmanager.com\/","name":"ProjectManager","description":"The Best Project Management Software for Managing your Projects","publisher":{"@id":"https:\/\/www.projectmanager.com\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.projectmanager.com\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/www.projectmanager.com\/#organization","name":"ProjectManager","url":"https:\/\/www.projectmanager.com\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.projectmanager.com\/#\/schema\/logo\/image\/","url":"\/wp-content\/uploads\/2026\/06\/ProjectManager-Logo-for-Website.png","contentUrl":"\/wp-content\/uploads\/2026\/06\/ProjectManager-Logo-for-Website.png","width":696,"height":696,"caption":"ProjectManager"},"image":{"@id":"https:\/\/www.projectmanager.com\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/projectmanage\/","https:\/\/www.linkedin.com\/company\/projectmanager.com\/","https:\/\/www.youtube.com\/user\/projectmanagervideos","https:\/\/en.wikipedia.org\/wiki\/ProjectManager.com"],"description":"ProjectManager is a project and portfolio management software that offers online project management tools like Gantt charts, dashboards, kanban boards, task management features and more. With advanced planning and scheduling, automated cost and time tracking, risk analysis and resource management, our platform ensures flawless execution for construction, manufacturing and professional services teams, while providing unbeatable insights at every stage.","legalName":"ProjectManager.com, Inc.","foundingDate":"2008-01-01","numberOfEmployees":{"@type":"QuantitativeValue","minValue":"11","maxValue":"50"}},{"@type":"Person","@id":"https:\/\/www.projectmanager.com\/#\/schema\/person\/83c2340d10ac161661864c1938cd4953","name":"Peter Landau","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/secure.gravatar.com\/avatar\/7521970efa63d95fa368e8426d2b1e51db76ddf997de4e0377dc781de5d97489?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/7521970efa63d95fa368e8426d2b1e51db76ddf997de4e0377dc781de5d97489?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/7521970efa63d95fa368e8426d2b1e51db76ddf997de4e0377dc781de5d97489?s=96&d=mm&r=g","caption":"Peter Landau"},"description":"Peter is the Content Editor at ProjectManager.com. He has worked as a writer and editor on print, digital and mobile platforms for both consumer and trade publications.","sameAs":["https:\/\/pmargo.wpengine.com","https:\/\/www.linkedin.com\/pub\/peter-landau\/3\/572\/12"],"knowsAbout":["Project management","Project planning","Blogs"],"knowsLanguage":["English"],"jobTitle":"Project Management Expert Writer","worksFor":"ProjectManager.com","url":"https:\/\/www.projectmanager.com\/author\/peterlandau"}]}},"_links":{"self":[{"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/posts\/49088","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/users\/18"}],"replies":[{"embeddable":true,"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/comments?post=49088"}],"version-history":[{"count":0,"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/posts\/49088\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/media\/68123"}],"wp:attachment":[{"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/media?parent=49088"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/categories?post=49088"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/tags?post=49088"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}