{"id":54092,"date":"2020-11-11T13:30:56","date_gmt":"2020-11-11T19:30:56","guid":{"rendered":"https:\/\/www.projectmanager.com\/?p=54092"},"modified":"2026-04-28T14:19:12","modified_gmt":"2026-04-28T19:19:12","slug":"schedule-baseline-make-one","status":"publish","type":"post","link":"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one","title":{"rendered":"What&#8217;s a Schedule Baseline &#038; How Do I Make One?"},"content":{"rendered":"<p><span class=\"blog-post-lead\">Before you start a project, you have to think about time.<\/span> It&#8217;s the most important variable that can impact your plan. How can you get what you need to be done in the time you have to do it? To accomplish this, one must create a schedule.<\/p>\n<p>A <a href=\"\/guides\/project-scheduling\">schedule<\/a> is a key to project planning, but schedules are just a framework. Once you act on it, executing your project task by task, the schedule changes. How can you make sure you stay on schedule and keep your project on track?<\/p>\n<p>That\u2019s where creating a baseline comes in. By creating a baseline project plan and a baseline schedule, you have the means to compare where you are in executing the project\u2014and if that aligns with where you intended to be at that time.<\/p>\n<h2>What Is a Schedule Baseline?<\/h2>\n<p>Whether you call it a baseline schedule or a schedule baseline, the term refers to the finished and approved schedule. The schedule baseline can be used as a tool to measure performance by reporting on <a href=\"https:\/\/www.projectmanager.com\/blog\/schedule-variance-what-is-it-how-do-i-calculate-it\">schedule variance.<\/a> That is, the schedule baseline can be used to compare where you planned to be at a certain time in the project against where the data shows you are.<\/p>\n<p><strong>Related:<\/strong> <a href=\"\/blog\/project-scheduling-templates\">Project Scheduling Templates<\/a><\/p>\n<p>As you know, the schedule for a project is a collection of tasks that must be completed over a specific timeline to reach the final deliverable for the project. Therefore, the schedule baseline is a way to capture this finalized schedule and use it as a benchmark to measure your progress in executing the project.<\/p>\n<p>The schedule baseline captures changes in your schedule that occur due to the <a href=\"https:\/\/www.projectmanager.com\/blog\/risk-management-process-steps\">development of risks.<\/a> Using a baseline schedule means you can see these variations in your schedule sooner, rather than later, and make adjustments quickly to stay on track.<\/p>\n<p>With ProjectManager, you can set a schedule baseline with your Gantt chart. As the project unfolds and your team updates their progress, you can track your performance compared to your baseline. There&#8217;s no easier way to monitor your schedule and meet your deadlines. Sign up for a free trial today.<\/p>\n<figure id=\"attachment_63415\" aria-describedby=\"caption-attachment-63415\" style=\"width: 1553px\" class=\"wp-caption aligncenter\"><a href=\"https:\/\/www.projectmanager.com\/freetrial\"><img loading=\"lazy\" decoding=\"async\" class=\"wp-image-63415 size-full\" src=\"\/wp-content\/uploads\/2022\/07\/Construction-Gantt-Task-Info-CTA-BUTTON-1.jpg\" alt=\"Gantt chart with schedule baseline\" width=\"1553\" height=\"834\" srcset=\"\/wp-content\/uploads\/2022\/07\/Construction-Gantt-Task-Info-CTA-BUTTON-1.jpg 1553w, \/wp-content\/uploads\/2022\/07\/Construction-Gantt-Task-Info-CTA-BUTTON-1-600x322.jpg 600w, \/wp-content\/uploads\/2022\/07\/Construction-Gantt-Task-Info-CTA-BUTTON-1-300x161.jpg 300w, \/wp-content\/uploads\/2022\/07\/Construction-Gantt-Task-Info-CTA-BUTTON-1-768x412.jpg 768w, \/wp-content\/uploads\/2022\/07\/Construction-Gantt-Task-Info-CTA-BUTTON-1-1536x825.jpg 1536w, \/wp-content\/uploads\/2022\/07\/Construction-Gantt-Task-Info-CTA-BUTTON-1-450x242.jpg 450w\" sizes=\"auto, (max-width: 1553px) 100vw, 1553px\" \/><\/a><figcaption id=\"caption-attachment-63415\" class=\"wp-caption-text\">Build a baseline with planned start and end dates on a Gantt chart. <strong><a href=\"\/software\/gantt-chart\">Learn more<\/a><\/strong><\/figcaption><\/figure>\n<h2>Why Use a Baseline Schedule?<\/h2>\n<p>The obvious reason to use a baseline schedule is that, well, it helps you stay on schedule. Without one, it\u2019s like you\u2019re working outside of the current context of your project. There\u2019s no way to know where <em>should<\/em> be in the schedule because there\u2019s no benchmark to compare your progress to.<\/p>\n<p>Projects rarely go by without numerous issues cropping up. There can be a minor mishap or a major one. Regardless of the severity of the problem, the repercussions can inevitably ripple through your schedule, leaving deadlines disrupted in its wake. You\u2019ll need to <a href=\"https:\/\/www.projectmanager.com\/blog\/resource-allocation\">reallocate resources<\/a> to steady your project.<\/p>\n<div class=\"template-download-holder\">\n\t<div class=\"template-download-image-holder\">\n\t\t<img loading=\"lazy\" decoding=\"async\" width=\"1600\" height=\"703\" src=\"\/wp-content\/uploads\/2024\/09\/Gantt-chart-template-2024-generic-1600x703.png\" class=\"attachment-large size-large\" alt=\"\" srcset=\"\/wp-content\/uploads\/2024\/09\/Gantt-chart-template-2024-generic-1600x703.png 1600w, \/wp-content\/uploads\/2024\/09\/Gantt-chart-template-2024-generic-600x263.png 600w, \/wp-content\/uploads\/2024\/09\/Gantt-chart-template-2024-generic-300x132.png 300w, \/wp-content\/uploads\/2024\/09\/Gantt-chart-template-2024-generic-768x337.png 768w, \/wp-content\/uploads\/2024\/09\/Gantt-chart-template-2024-generic-1536x675.png 1536w, \/wp-content\/uploads\/2024\/09\/Gantt-chart-template-2024-generic-450x198.png 450w, \/wp-content\/uploads\/2024\/09\/Gantt-chart-template-2024-generic.png 1676w\" sizes=\"auto, (max-width: 1600px) 100vw, 1600px\" \/>\t<\/div><p class=\"intro\">Get your free<\/p>\n<h3>Gantt Chart Template<\/h3>\n<p class=\"subtitle\">\n\tUse this free Gantt Chart Template to manage your projects better.<\/p>\n\t<a class=\"button green\" href=\"https:\/\/www.projectmanager.com\/templates\/gantt-chart-template\">Get the Template<\/a>\n<\/div> \n\n<p>&nbsp;<\/p>\n<p>That means changing parts of the schedule to respond to the changes and stay on track to meet your final deadline. In the constant flux of changes and setbacks, though, the schedule baseline <em>stays firm.<\/em> It\u2019s the constant in the sea of change that is a project, allowing you to navigate successfully when a storm takes you into uncharted waters.<\/p>\n<p>Of course, there are many different types of baselines. All of them are important. The baseline schedule keeps you on target and is related to the baseline project plan, in that the schedule is part of the larger <a href=\"https:\/\/www.projectmanager.com\/project-planning\">project plan.<\/a> But the baseline schedule incorporates business assets and resources, so you can allocate them correctly to stay on schedule.<\/p>\n<h2>How to Make a Schedule Baseline<\/h2>\n<p>Before you can baseline your schedule, you need to have a schedule. That starts by collecting all the tasks you\u2019ll need to execute to lead to your final deliverable.<\/p>\n<h3>Identify Tasks<\/h3>\n<p>Use a <a href=\"https:\/\/www.projectmanager.com\/work-breakdown-structure\">work breakdown structure<\/a> to work backward from your final deliverable. This tool makes sure you don\u2019t leave out any steps. To make a successful schedule, you need to first thoroughly define every task. Having <a href=\"https:\/\/www.projectmanager.com\/blog\/planning-meeting-with-checklist\">planning meetings<\/a> with your team and stakeholders will help make sure you don\u2019t leave any important steps out of your schedule. You can also use historical data when researching similar projects.<\/p>\n<h3>Determine Duration<\/h3>\n<p>Once you have all your activities lined up, you\u2019ll need to <a href=\"https:\/\/www.projectmanager.com\/blog\/time-estimation-for-project-managers\">estimate how long they\u2019ll take<\/a> to complete. There are a number of techniques to help you get an accurate figure. For quicker results, there\u2019s analogous estimating, which refers back to the time it took to complete similar past projects. There are also three-point estimates, which use a formula to calculate parameters of most likely, optimistic and pessimistic. Of course, there are other tools. Choose the one right for you and your project.<\/p>\n<h3>Set Milestones<\/h3>\n<p>Projects are big and tasks are small. <a href=\"https:\/\/www.projectmanager.com\/blog\/milestones-project-management\">Milestones<\/a> are the steps between those two points. They are usually used to mark the end of one project phase and the beginning of the next. However, you can use a milestone to determine any major point in the project.<\/p>\n<h3>Identify Dependencies<\/h3>\n<p>Some of the tasks you collected are going to stand alone, while others are going to be <a href=\"https:\/\/www.projectmanager.com\/blog\/manage-task-dependencies\">dependent on others.<\/a> That is, they won\u2019t be able to start or stop until another starts or stops. These dependent tasks can cause problems later on in the project if you don\u2019t identify them.<\/p>\n<h3>Add Resources<\/h3>\n<p>Tasks don&#8217;t complete themselves. You need to <a href=\"https:\/\/www.projectmanager.com\/resource-management\">attach resources<\/a> to them. Resources can be team members, materials, tools, etc. These all have associated costs and also estimated duration to determine how long you\u2019ll need them for.<\/p>\n<h3>Set Baseline<\/h3>\n<p>Now you have a project schedule. Setting the baseline is just freezing this data\u2014taking a snapshot of it. You\u2019ll need that to compare your progress as you move into the execution phase of the project.<\/p>\n<p>In the next section, we&#8217;ll show you how easy it is to do this in ProjectManager or, if you prefer, you can watch this short tutorial video.<\/p>\n<div itemprop='video' itemscope itemtype='http:\/\/schema.org\/VideoObject' id='pmw_9tjhryzghn'><div  data-pmwistia-type='inline'  data-pmwistia-id='9tjhryzghn' data-pmwistia-iteration='1' class='pmwistia ' style=''><a target='_blank' rel='noopener' href='https:\/\/fast.wistia.net\/embed\/iframe\/9tjhryzghn?autoplay=true' data-pmwistia-width='1000' data-pmwistia-height='563' data-pmwistia-style='border:none;padding:0;max-width:100%;' class='pmwistia-trigger ' style=''><img  alt='Project management training video (9tjhryzghn)' loading='lazy'  width='900'  height='506'  src='https:\/\/embed-ssl.wistia.com\/deliveries\/1781c8853c8876501de1fb95bb2d24a0.jpg?image_crop_resized=900x506&amp;image_play_button=true&amp;image_play_button_size=2x&amp;image_play_button_color=1b4560e0' class='aligncenter size-full pmwistia-img  pmwistia-img-replace  pmwistia-img-inline ' style=''><\/a><\/div><meta itemprop='name' content='Project Scheduling Software' \/><meta itemprop='description' content='Learn about project scheduling software and its benefits' \/><link itemprop='embedUrl' href='https:\/\/fast.wistia.net\/embed\/iframe\/9tjhryzghn?autoplay=true' \/><meta itemprop='thumbnailUrl' content='https:\/\/embed-ssl.wistia.com\/deliveries\/1781c8853c8876501de1fb95bb2d24a0.jpg?image_crop_resized=900x506' \/><meta itemprop='uploadDate' content='2022-07-12T21:47:44+0000' \/><meta itemprop='duration' content='PT0H2M30S' \/><meta itemprop='contentUrl' content='https:\/\/embed-ssl.wistia.com\/deliveries\/37a494bd7875eeec1a3b6f5d269cdd583c46bc06.bin' \/><div itemprop='interactionStatistic' itemtype='http:\/\/schema.org\/InteractionCounter' itemscope><meta itemprop='userInteractionCount' content='13882' \/><meta itemprop='interactionType' itemtype='http:\/\/schema.org\/WatchAction' \/><\/div><\/div>\n<h2>How to Make a Schedule Baseline in ProjectManager<\/h2>\n<p>Once you\u2019ve made your schedule, save it. Now, you have a schedule baseline and can use this document to compare to your actual progress when you execute the project. But there is a more efficient way to calculate your project variance.<\/p>\n<p>Time is a valuable resource in any project, and using cloud-based <a href=\"\/software\/scheduling\">project scheduling software<\/a> like ProjectManager is how you can save time and money while boosting your project\u2019s productivity. Here\u2019s how it works.<\/p>\n<p>First, you\u2019ll want to build out your schedule on our <a href=\"https:\/\/www.projectmanager.com\/software\/gantt-chart\">online Gantt chart.<\/a> Import the tasks or use one of our industry-specific templates to start. Just like any schedule, you want to add the start and end dates. Then, the Gantt charts your project over a timeline. But here\u2019s where things get interesting.<\/p>\n<figure id=\"attachment_61844\" aria-describedby=\"caption-attachment-61844\" style=\"width: 992px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" class=\"wp-image-61844 size-full\" src=\"\/wp-content\/uploads\/2022\/03\/pm-gantt-screenshot.png\" alt=\"ProjectManager Gantt chart\" width=\"992\" height=\"518\" srcset=\"\/wp-content\/uploads\/2022\/03\/pm-gantt-screenshot.png 992w, \/wp-content\/uploads\/2022\/03\/pm-gantt-screenshot-600x313.png 600w, \/wp-content\/uploads\/2022\/03\/pm-gantt-screenshot-300x157.png 300w, \/wp-content\/uploads\/2022\/03\/pm-gantt-screenshot-768x401.png 768w, \/wp-content\/uploads\/2022\/03\/pm-gantt-screenshot-450x235.png 450w\" sizes=\"auto, (max-width: 992px) 100vw, 992px\" \/><figcaption id=\"caption-attachment-61844\" class=\"wp-caption-text\">Use a Gantt chart to build and manage your project schedule.<\/figcaption><\/figure>\n<h3>Add Milestones to Create Phases<\/h3>\n<p>Break up the larger schedule into more manageable parts with our milestone feature, which can divide the project into phases or indicate major deadlines. The Gantt can be further customized by color.<\/p>\n<figure id=\"attachment_61514\" aria-describedby=\"caption-attachment-61514\" style=\"width: 1568px\" class=\"wp-caption aligncenter\"><img loading=\"lazy\" decoding=\"async\" class=\"wp-image-61514 size-full\" src=\"\/wp-content\/uploads\/2022\/03\/Gantt_Marketing_Wide_Zoom-150_Customize-Colors.jpg\" alt=\"ProjectManager's Gantt chart with color choices selected\" width=\"1568\" height=\"817\" srcset=\"\/wp-content\/uploads\/2022\/03\/Gantt_Marketing_Wide_Zoom-150_Customize-Colors.jpg 1568w, \/wp-content\/uploads\/2022\/03\/Gantt_Marketing_Wide_Zoom-150_Customize-Colors-600x313.jpg 600w, \/wp-content\/uploads\/2022\/03\/Gantt_Marketing_Wide_Zoom-150_Customize-Colors-300x156.jpg 300w, \/wp-content\/uploads\/2022\/03\/Gantt_Marketing_Wide_Zoom-150_Customize-Colors-768x400.jpg 768w, \/wp-content\/uploads\/2022\/03\/Gantt_Marketing_Wide_Zoom-150_Customize-Colors-1536x800.jpg 1536w, \/wp-content\/uploads\/2022\/03\/Gantt_Marketing_Wide_Zoom-150_Customize-Colors-450x234.jpg 450w\" sizes=\"auto, (max-width: 1568px) 100vw, 1568px\" \/><figcaption id=\"caption-attachment-61514\" class=\"wp-caption-text\">Custom colors help you differentiate teams, phases and more.<\/figcaption><\/figure>\n<h3>Link Dependencies<\/h3>\n<p>Then, link dependencies, so they don\u2019t sneak up on you during execution. If there are changes during execution, our Gantt can be edited simply by dragging and dropping the task to the new date.<\/p>\n<img loading=\"lazy\" decoding=\"async\" class=\"aligncenter wp-image-63408 size-full\" src=\"\/wp-content\/uploads\/2022\/07\/Construction-Project-Gantt-Linked-Tasks.jpg\" alt=\"schedule baseline with dependencies\" width=\"2559\" height=\"1371\" srcset=\"\/wp-content\/uploads\/2022\/07\/Construction-Project-Gantt-Linked-Tasks.jpg 2559w, \/wp-content\/uploads\/2022\/07\/Construction-Project-Gantt-Linked-Tasks-600x321.jpg 600w, \/wp-content\/uploads\/2022\/07\/Construction-Project-Gantt-Linked-Tasks-1600x857.jpg 1600w, \/wp-content\/uploads\/2022\/07\/Construction-Project-Gantt-Linked-Tasks-300x161.jpg 300w, \/wp-content\/uploads\/2022\/07\/Construction-Project-Gantt-Linked-Tasks-768x411.jpg 768w, \/wp-content\/uploads\/2022\/07\/Construction-Project-Gantt-Linked-Tasks-1536x823.jpg 1536w, \/wp-content\/uploads\/2022\/07\/Construction-Project-Gantt-Linked-Tasks-2048x1097.jpg 2048w, \/wp-content\/uploads\/2022\/07\/Construction-Project-Gantt-Linked-Tasks-450x241.jpg 450w\" sizes=\"auto, (max-width: 2559px) 100vw, 2559px\" \/>\n<h3>Setting the Baseline<\/h3>\n<p>As noted, setting the baseline is how you measure project variance when you\u2019re executing the tasks. Therefore, once you\u2019ve completed your plan, you want to set the schedule baseline. All you have to do with our Gantt tool is to click the advanced settings. There, you\u2019ll see an option to set the baseline. It\u2019s that easy.<\/p>\n<img loading=\"lazy\" decoding=\"async\" class=\"aligncenter wp-image-68749 size-full\" src=\"\/wp-content\/uploads\/2020\/11\/set-baseline-picture.jpg\" alt=\"Set schedule baseline on ProjectManager\" width=\"1723\" height=\"708\" srcset=\"\/wp-content\/uploads\/2020\/11\/set-baseline-picture.jpg 1723w, \/wp-content\/uploads\/2020\/11\/set-baseline-picture-600x247.jpg 600w, \/wp-content\/uploads\/2020\/11\/set-baseline-picture-1600x657.jpg 1600w, \/wp-content\/uploads\/2020\/11\/set-baseline-picture-300x123.jpg 300w, \/wp-content\/uploads\/2020\/11\/set-baseline-picture-768x316.jpg 768w, \/wp-content\/uploads\/2020\/11\/set-baseline-picture-1536x631.jpg 1536w, \/wp-content\/uploads\/2020\/11\/set-baseline-picture-450x185.jpg 450w\" sizes=\"auto, (max-width: 1723px) 100vw, 1723px\" \/>\n<p>When you have set your baseline, the planned start and finish dates will populate the baseline start and finish columns. These dates will not change unless you reset your baseline and override them.<\/p>\n<p>Our <a href=\"https:\/\/www.projectmanager.com\/software\/reporting\">one-click reports<\/a> include a project variance report that will compare your actual to planned progress. This is a great way to calculate project buffer, which is how much time you can add to a task without impacting the overall schedule.<\/p>\n<p><em><a href=\"https:\/\/www.projectmanager.com\/pricing\/\">ProjectManager<\/a> is an award-winning tool that helps managers schedule and gives them the tools they need to keep that schedule on track. From scheduling baselines to tracking project variance, you have control. Organize tasks, assign resources and monitor it all in real-time.<\/em><\/p>\n","protected":false},"excerpt":{"rendered":"<p>Before you start a project, you have to think about time. It&#8217;s the most important variable that can impact your&#8230;<br \/><a class=\"excerpt-read-more button blue\" href=\"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one\">Read More<\/a><\/p>\n","protected":false},"author":69,"featured_media":54311,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_yoast_wpseo_meta-robots-noindex":0,"_yoast_wpseo_canonical":"","_yoast_wpseo_opengraph-title":"","_yoast_wpseo_opengraph-description":"","_yoast_wpseo_opengraph-image":"","_yoast_wpseo_twitter-title":"","_yoast_wpseo_twitter-description":"","head_code_insert":"","footnotes":""},"categories":[195,193,131,252],"tags":[],"class_list":["post-54092","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-planning","category-project-management","category-blog","category-scheduling"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO Premium plugin v28.3 (Yoast SEO v28.4) - https:\/\/yoast.com\/product\/yoast-seo-premium-wordpress\/ -->\n<title>What&#039;s a Schedule Baseline &amp; How Do I Make One?<\/title>\n<meta name=\"description\" content=\"Schedules organize tasks and resources against a timeline, but how do you know if you&#039;re on track? That&#039;s where a baseline comes in.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"What&#039;s a Schedule Baseline &amp; How Do I Make One?\" \/>\n<meta property=\"og:description\" content=\"Schedules organize tasks and resources against a timeline, but how do you know if you&#039;re on track? That&#039;s where a baseline comes in.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one\" \/>\n<meta property=\"og:site_name\" content=\"ProjectManager\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/projectmanage\/\" \/>\n<meta property=\"article:published_time\" content=\"2020-11-11T19:30:56+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2026-04-28T19:19:12+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/www.projectmanager.com\/wp-content\/uploads\/2020\/11\/201110_Blog_Feature_Baseline_Schedule-scaled.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"2560\" \/>\n\t<meta property=\"og:image:height\" content=\"1440\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"Marshall Simmons\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Marshall Simmons\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"8 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/schedule-baseline-make-one#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/schedule-baseline-make-one\"},\"author\":{\"name\":\"Marshall Simmons\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#\\\/schema\\\/person\\\/70dff386ee1866ea13fb6def6f251714\"},\"headline\":\"What&#8217;s a Schedule Baseline &#038; How Do I Make One?\",\"datePublished\":\"2020-11-11T19:30:56+00:00\",\"dateModified\":\"2026-04-28T19:19:12+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/schedule-baseline-make-one\"},\"wordCount\":1472,\"publisher\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/schedule-baseline-make-one#primaryimage\"},\"thumbnailUrl\":\"\\\/wp-content\\\/uploads\\\/2020\\\/11\\\/201110_Blog_Feature_Baseline_Schedule-scaled.jpg\",\"articleSection\":[\"Planning\",\"Project Management\",\"Project Management Blog\",\"Scheduling\"],\"inLanguage\":\"en-US\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/schedule-baseline-make-one\",\"url\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/schedule-baseline-make-one\",\"name\":\"What's a Schedule Baseline & How Do I Make One?\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/schedule-baseline-make-one#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/schedule-baseline-make-one#primaryimage\"},\"thumbnailUrl\":\"\\\/wp-content\\\/uploads\\\/2020\\\/11\\\/201110_Blog_Feature_Baseline_Schedule-scaled.jpg\",\"datePublished\":\"2020-11-11T19:30:56+00:00\",\"dateModified\":\"2026-04-28T19:19:12+00:00\",\"description\":\"Schedules organize tasks and resources against a timeline, but how do you know if you're on track? That's where a baseline comes in.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/schedule-baseline-make-one#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/schedule-baseline-make-one\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/schedule-baseline-make-one#primaryimage\",\"url\":\"\\\/wp-content\\\/uploads\\\/2020\\\/11\\\/201110_Blog_Feature_Baseline_Schedule-scaled.jpg\",\"contentUrl\":\"\\\/wp-content\\\/uploads\\\/2020\\\/11\\\/201110_Blog_Feature_Baseline_Schedule-scaled.jpg\",\"width\":2560,\"height\":1440,\"caption\":\"Feature Baseline Schedule\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/blog\\\/schedule-baseline-make-one#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/www.projectmanager.com\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"What&#8217;s a Schedule Baseline &#038; How Do I Make One?\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#website\",\"url\":\"https:\\\/\\\/www.projectmanager.com\\\/\",\"name\":\"ProjectManager\",\"description\":\"The Best Project Management Software for Managing your Projects\",\"publisher\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/www.projectmanager.com\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#organization\",\"name\":\"ProjectManager\",\"url\":\"https:\\\/\\\/www.projectmanager.com\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"\\\/wp-content\\\/uploads\\\/2026\\\/06\\\/ProjectManager-Logo-for-Website.png\",\"contentUrl\":\"\\\/wp-content\\\/uploads\\\/2026\\\/06\\\/ProjectManager-Logo-for-Website.png\",\"width\":696,\"height\":696,\"caption\":\"ProjectManager\"},\"image\":{\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#\\\/schema\\\/logo\\\/image\\\/\"},\"sameAs\":[\"https:\\\/\\\/www.facebook.com\\\/projectmanage\\\/\",\"https:\\\/\\\/www.linkedin.com\\\/company\\\/projectmanager.com\\\/\",\"https:\\\/\\\/www.youtube.com\\\/user\\\/projectmanagervideos\",\"https:\\\/\\\/en.wikipedia.org\\\/wiki\\\/ProjectManager.com\"],\"description\":\"ProjectManager is a project and portfolio management software that offers online project management tools like Gantt charts, dashboards, kanban boards, task management features and more. With advanced planning and scheduling, automated cost and time tracking, risk analysis and resource management, our platform ensures flawless execution for construction, manufacturing and professional services teams, while providing unbeatable insights at every stage.\",\"legalName\":\"ProjectManager.com, Inc.\",\"foundingDate\":\"2008-01-01\",\"numberOfEmployees\":{\"@type\":\"QuantitativeValue\",\"minValue\":\"11\",\"maxValue\":\"50\"}},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/www.projectmanager.com\\\/#\\\/schema\\\/person\\\/70dff386ee1866ea13fb6def6f251714\",\"name\":\"Marshall Simmons\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/ae3f28a817a1063919a0259debb431cea1fbef8f07dc4500cb497e1dba865b56?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/ae3f28a817a1063919a0259debb431cea1fbef8f07dc4500cb497e1dba865b56?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/ae3f28a817a1063919a0259debb431cea1fbef8f07dc4500cb497e1dba865b56?s=96&d=mm&r=g\",\"caption\":\"Marshall Simmons\"},\"description\":\"Marshall Simmons is the Content Manager at ProjectManager.com. Based in Central Texas, he brings over five years of writing and editing experience to the website, blog and YouTube channel.\",\"knowsAbout\":[\"Project management\",\"Project planning\",\"Blogs\"],\"knowsLanguage\":[\"English\"],\"jobTitle\":\"Project Management Expert Writer\",\"worksFor\":\"ProjectManager.com\",\"url\":\"https:\\\/\\\/www.projectmanager.com\\\/author\\\/marshallsimmons\"}]}<\/script>\n<!-- \/ Yoast SEO Premium plugin. -->","yoast_head_json":{"title":"What's a Schedule Baseline & How Do I Make One?","description":"Schedules organize tasks and resources against a timeline, but how do you know if you're on track? That's where a baseline comes in.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one","og_locale":"en_US","og_type":"article","og_title":"What's a Schedule Baseline & How Do I Make One?","og_description":"Schedules organize tasks and resources against a timeline, but how do you know if you're on track? That's where a baseline comes in.","og_url":"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one","og_site_name":"ProjectManager","article_publisher":"https:\/\/www.facebook.com\/projectmanage\/","article_published_time":"2020-11-11T19:30:56+00:00","article_modified_time":"2026-04-28T19:19:12+00:00","og_image":[{"width":2560,"height":1440,"url":"https:\/\/www.projectmanager.com\/wp-content\/uploads\/2020\/11\/201110_Blog_Feature_Baseline_Schedule-scaled.jpg","type":"image\/jpeg"}],"author":"Marshall Simmons","twitter_card":"summary_large_image","twitter_misc":{"Written by":"Marshall Simmons","Est. reading time":"8 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one#article","isPartOf":{"@id":"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one"},"author":{"name":"Marshall Simmons","@id":"https:\/\/www.projectmanager.com\/#\/schema\/person\/70dff386ee1866ea13fb6def6f251714"},"headline":"What&#8217;s a Schedule Baseline &#038; How Do I Make One?","datePublished":"2020-11-11T19:30:56+00:00","dateModified":"2026-04-28T19:19:12+00:00","mainEntityOfPage":{"@id":"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one"},"wordCount":1472,"publisher":{"@id":"https:\/\/www.projectmanager.com\/#organization"},"image":{"@id":"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one#primaryimage"},"thumbnailUrl":"\/wp-content\/uploads\/2020\/11\/201110_Blog_Feature_Baseline_Schedule-scaled.jpg","articleSection":["Planning","Project Management","Project Management Blog","Scheduling"],"inLanguage":"en-US"},{"@type":"WebPage","@id":"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one","url":"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one","name":"What's a Schedule Baseline & How Do I Make One?","isPartOf":{"@id":"https:\/\/www.projectmanager.com\/#website"},"primaryImageOfPage":{"@id":"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one#primaryimage"},"image":{"@id":"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one#primaryimage"},"thumbnailUrl":"\/wp-content\/uploads\/2020\/11\/201110_Blog_Feature_Baseline_Schedule-scaled.jpg","datePublished":"2020-11-11T19:30:56+00:00","dateModified":"2026-04-28T19:19:12+00:00","description":"Schedules organize tasks and resources against a timeline, but how do you know if you're on track? That's where a baseline comes in.","breadcrumb":{"@id":"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one#primaryimage","url":"\/wp-content\/uploads\/2020\/11\/201110_Blog_Feature_Baseline_Schedule-scaled.jpg","contentUrl":"\/wp-content\/uploads\/2020\/11\/201110_Blog_Feature_Baseline_Schedule-scaled.jpg","width":2560,"height":1440,"caption":"Feature Baseline Schedule"},{"@type":"BreadcrumbList","@id":"https:\/\/www.projectmanager.com\/blog\/schedule-baseline-make-one#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/www.projectmanager.com\/"},{"@type":"ListItem","position":2,"name":"What&#8217;s a Schedule Baseline &#038; How Do I Make One?"}]},{"@type":"WebSite","@id":"https:\/\/www.projectmanager.com\/#website","url":"https:\/\/www.projectmanager.com\/","name":"ProjectManager","description":"The Best Project Management Software for Managing your Projects","publisher":{"@id":"https:\/\/www.projectmanager.com\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.projectmanager.com\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/www.projectmanager.com\/#organization","name":"ProjectManager","url":"https:\/\/www.projectmanager.com\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.projectmanager.com\/#\/schema\/logo\/image\/","url":"\/wp-content\/uploads\/2026\/06\/ProjectManager-Logo-for-Website.png","contentUrl":"\/wp-content\/uploads\/2026\/06\/ProjectManager-Logo-for-Website.png","width":696,"height":696,"caption":"ProjectManager"},"image":{"@id":"https:\/\/www.projectmanager.com\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/projectmanage\/","https:\/\/www.linkedin.com\/company\/projectmanager.com\/","https:\/\/www.youtube.com\/user\/projectmanagervideos","https:\/\/en.wikipedia.org\/wiki\/ProjectManager.com"],"description":"ProjectManager is a project and portfolio management software that offers online project management tools like Gantt charts, dashboards, kanban boards, task management features and more. With advanced planning and scheduling, automated cost and time tracking, risk analysis and resource management, our platform ensures flawless execution for construction, manufacturing and professional services teams, while providing unbeatable insights at every stage.","legalName":"ProjectManager.com, Inc.","foundingDate":"2008-01-01","numberOfEmployees":{"@type":"QuantitativeValue","minValue":"11","maxValue":"50"}},{"@type":"Person","@id":"https:\/\/www.projectmanager.com\/#\/schema\/person\/70dff386ee1866ea13fb6def6f251714","name":"Marshall Simmons","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/secure.gravatar.com\/avatar\/ae3f28a817a1063919a0259debb431cea1fbef8f07dc4500cb497e1dba865b56?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/ae3f28a817a1063919a0259debb431cea1fbef8f07dc4500cb497e1dba865b56?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/ae3f28a817a1063919a0259debb431cea1fbef8f07dc4500cb497e1dba865b56?s=96&d=mm&r=g","caption":"Marshall Simmons"},"description":"Marshall Simmons is the Content Manager at ProjectManager.com. Based in Central Texas, he brings over five years of writing and editing experience to the website, blog and YouTube channel.","knowsAbout":["Project management","Project planning","Blogs"],"knowsLanguage":["English"],"jobTitle":"Project Management Expert Writer","worksFor":"ProjectManager.com","url":"https:\/\/www.projectmanager.com\/author\/marshallsimmons"}]}},"_links":{"self":[{"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/posts\/54092","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/users\/69"}],"replies":[{"embeddable":true,"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/comments?post=54092"}],"version-history":[{"count":0,"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/posts\/54092\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/media\/54311"}],"wp:attachment":[{"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/media?parent=54092"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/categories?post=54092"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.projectmanager.com\/wp-json\/wp\/v2\/tags?post=54092"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}